Victory in the first battle! Yalong River hydropower Raba Mountain wind power project single-blade fan lifting

Release time: Jul. 13, 2023

Victory in the first battle! Yalong River hydropower Raba Mountain wind power project single-blade fan lifting

In recent years, wind turbines tend to be large, and the diameter of the impeller is getting larger, and the overall hoisting of the traditional impeller is facing multiple challenges. In view of the large windward area of the large impeller, the lateral load may exceed the anti-lateral ability of the crane in extreme cases, the giant power rigging optimizes the traditional wind power hoisting scheme according to local conditions. To maximize the solution of large impeller ground assembly covers a large area, in the mountain, woodland lifting construction limited problems.

Victory in the first battle! Yalong River hydropower Raba Mountain wind power project single-blade fan lifting

If the traditional impeller integral lifting method is used, the upper limit of allowable wind speed is low, only 8 m/s; The hoisting platform has a large area and a large amount of excavation and filling. It is difficult to arrange the position of the main crane and auxiliary crane, and it is difficult to slide the impeller tail.

Victory in the first battle! Yalong River hydropower Raba Mountain wind power project single-blade fan lifting

Using single blade hoisting can solve these problems skillfully. Single blade hoisting is the preferred installation method for large capacity wind turbines with impeller diameter of more than 160 meters, and it is also one of the current mainstream installation technologies. Sichuan Province in the past, because of the small capacity of single fan, small impeller diameter, hoisting constraints are few, all adopt the impeller lifting method.

Victory in the first battle! Yalong River hydropower Raba Mountain wind power project single-blade fan lifting


In contrast, single-blade lifting is less limited by wind speed and terrain. The upper limit of hoisting wind speed is increased from 8 m/s to 10 m/s, extending the hoisting operation window period, effectively reducing the construction time and overall cost of the project. At the same time, the single blade hoisting can greatly reduce the area of the construction site, reduce the amount of digging and filling and vegetation damage because it avoids the ground assembly of the impeller. It is estimated that at least 30% of the floor area can be saved.